News

Aganang cement plant to come on line by end-July

17 October 2014

Cement producer Sephaku Cement (SepCem) hopes to bring its Aganang cement production facility on line by end-July, following commissioning during the first half of the year, Sephaku Holdings CEO Dr Lelau Mohuba said on Monday.

SepCem was 36% owned by Sephaku Holdings, with Nigeria-listed Dangote Cement holding the remainder of the company.

Mohuba noted that the Aganang plant’s cold commissioning had been done in February, with hot commissioning having followed in March. “A dedicated operational preparedness team has ensured that SepCem meets its targets for completion and market readiness,” he said.

Along with SepCem’s Delmas plant, which started production in January, the Aganang plant brought SepCem’s yearly cement production capacity to 2.5-million tons.

“SepCem will ramp up cement volumes at both plants, not aggressively, but in line with market demand,” Mohuba noted, adding that the company expected to reach steady-state production during the 2015 calendar year.

He said that, from the company’s observations, the outlook was not as bad for the construction industry as was commonly believed, adding that SepCem was expecting to see an uptick in the market and was planning to ramp up its output accordingly.

SepCem MD Pieter Fourie said the company anticipated producing at 70% to 80% of its capacity over the next two to three years, in line with industry demand.

More information from Shalini Ammon, Tel:+27(0)12 684 6337 / www.sephakucement.co.za

For more articles such as this please visit our online edition: http://concrete.tv/more/concrete-trends

Read the latest issue

Latest Issue